Intersection Improvements
To accommodate the city's growth, this Capital Improvement Project will add lanes to improve capacity at seven (7) of the highest volume intersections in Frisco. Watch a Progress in Motion video highlighting the intersection improvements.
Lane closures are anticipated between 9 a.m. and 3:30 p.m. daily in an effort to keep existing lanes open during peak travel times. Please slow down and use caution in the work zone.
Additional information will be posted as developments in construction timelines and phases occur.
Intersections / Timeline
- Lebanon Road / FM 423 - complete
- Wade Boulevard / Preston Road - November 2023 start date
- Preston Road / Main Street - January 2024 start date
- Stonebrook Parkway / FM 423 - May 2024 start date
- Coit Road / SH 121 (TBD)
- Ohio Drive / Hillcrest Road (TBD)
- Warren Parkway / Preston Road (TBD)
The extension of Donnie Mayfield Way is also part of this project. The extension will reach the future site of an elevated storage tank on PGA Parkway.
Anticipated completion of all seven (7) intersections is Q2 2025.
Improvements include:
- addition of left turn lanes
- street lighting
- traffic signal adjustments
- storm drains
- sidewalks
- landscaping and irrigation adjustments associated with the roadway widenings
View the construction plans. (pdf)
Stonebrook Parkway / FM 423
Construction is anticipated to begin in early May 2024.
Read more about improvements in the area in this PDF.
Preston Road / Main Street - UPDATE
Construction Timeline
Phase 1 construction at Preston Road and Main Street is slated for completion on April 1st. Phase 2 will begin the following day. Phase 2 of construction is anticipated to last 12 weeks, which will complete the intersection improvements at this location.
Beginning Tuesday, April 2nd, traffic will shift to the new pavement on the east side of Preston Road. Expect additional delays as drivers become accustomed to the new traffic control patterns. Lane closures will continue between 9 a.m. and 3:30 p.m. daily in an effort to keep existing lanes open during peak travel times.
https://www.friscotexas.gov/documentcenter/view/31415/prestonmain-intersection-improvement-flyer
Read more about improvements in the area in this PDF.
Watch a Progress in Motion video about the Preston Road / Main Street intersection improvements.
Wade Boulevard / Preston Road
Construction continues on the intersection improvements.
Read more about improvements in the area.
Lebanon Road / FM 423
The intersection improvements at Lebanon Road and FM 423 are complete.
Read more.
Capital Improvements Project Dashboard
Keep up to date on all capital improvement projects active within the City of Frisco Engineering Services Department. The interactive map displays project locations, general construction timeframes and estimated construction costs. View the CIP Dashboard here.
Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project DashboardCapital Improvements Project Dashboard
Notes Concerning Construction Activity
Construction schedules change, sometimes with little notice, for any number of reasons. Please understand there will be changes. Construction work is dependent on the weather. Information regarding all construction timelines and activities is weather permitting. Rain will cancel most construction activity. In addition, certain activities require specific temperatures or dry weather for a previous number of days before execution. We appreciate your patience. Capital Improvements Project Dashboard Capital Improvements Project Dashboard